The site road network - 6.477 km in the proposal.


6.477 km of access tracks required.  Each 4.5m wide and 1 m deep.

28,000 cubic m of spoil to be removed from site and replaced by crushed rock or hardcore.


See below for a site map. Alongside each turbine location a hard standing 1m  deep will be constructed to provide a base for the crane and store the turbine components while the turbines are being assembled.


The photograph shows a section of a site access track at Rusholme.


It was this phase of the project which caused many of the problems for residents at Rusholme.